Pile Integrity Testing (PIT) - Quality Assurance
Foundation

Pile Integrity Testing (PIT) - Quality Assurance

31 July 2023
On Cloud Nine, Wellawatte

Following the completion of the piling phase, we conducted a comprehensive Pile Integrity Test (PIT) on the cast-in-situ piles. This non-destructive testing method uses sonic echoes to confirm the continuity, consistency, and structural integrity of each pile shaft. By verifying that there are no cracks or voids deep within the concrete, we ensure that the foundation is fully capable of supporting the building's design load.